Challenges in Cost Estimation under Uncertainty—A Case Study of the Decommissioning of Barsebäck Nuclear Power Plant

Published on Oct 20, 2016in Administrative Sciences
· DOI :10.3390/admsci6040014
Olav Torp5
Estimated H-index: 5
,
Ole Jonny Klakegg11
Estimated H-index: 11
Abstract
Cost estimation is an important part of project planning. Over the years different approaches have developed, taking uncertainty into account in the cost estimation processes in order to tackle the dynamic nature of projects. However, when implementing these approaches, some challenges have been revealed. The aim in a cost estimation process is to establish a realistic overview of the total project costs and its uncertainties. Even though tools and methods for taking uncertainty into account are implemented, projects with cost overruns are often seen. In this paper we look into some challenges with the practice in cost estimation processes and identify possible improvements to overcome them. The purpose of this paper is to illustrate better solutions to some of the major weaknesses identified in current cost estimation practice. We use a case study of decommissioning of Barseback Nuclear Power Plant to illustrate how to overcome these challenges. First of all, this is an interesting case with challenges related to the project and the cost estimation process, given the complexity in the situation and that very few have experiences related to decommission of nuclear power plants. Second, we applied an approach that is not yet commonly used to develop cost estimates for this kind of projects. The paper concludes that it is possible to improve the results of uncertainty analysis of cost estimates. A well prepared process, with a suitable group of experts that go through a well-structured process, focusing both on risks and opportunities and using a top-down approach can compensate for some of the challenges related to cost estimation under uncertainty.
  • References (25)
  • Citations (7)
📖 Papers frequently viewed together
2019
3 Authors (G. Nelis, ..., E. Widzyk-Capehart)
1 Citations
2003
4 Authors (M.B. Zaaijer, ..., H. B. Hendriks)
2 Citations
78% of Scinapse members use related papers. After signing in, all features are FREE.
References25
Newest
#1Ole Jonny Klakegg (NTNU: Norwegian University of Science and Technology)H-Index: 11
#2Steen LichtenbergH-Index: 1
Abstract Project Management and Cost Engineering have made tremendous advances but we still witness all too frequent severe budget overruns and delays. A solution to this mega problem of budget overruns actually exists. Use of the Successive Principle has demonstrated this during the later decennials. It has demonstrated in tough practice that it is possible to make accurate, unbiased statistical prognoses of the factual project cost or other important key figures. The results reported here may ...
4 CitationsSource
#1Moses T. Adoko (GW: George Washington University)H-Index: 1
#2Thomas A. Mazzuchi (GW: George Washington University)H-Index: 27
Last. Shahram Sarkani (GW: George Washington University)H-Index: 25
view all 3 authors...
While system complexity is on the rise across many product lines, the resources required to successfully design and implement complex systems remain constrained. Because financiers of complex systems development efforts actively monitor project implementation cost, project performance models are needed to help project managers predict their cost compliance and avoid cost overruns. This article describes recent research conducted by the authors to develop a cost overrun predictive model using fiv...
4 CitationsSource
#1Olugbenga Jide Olaniran (Curtin University)H-Index: 3
#2Peter E.D. Love (Curtin University)H-Index: 70
Last. Jane Matthews (Curtin University)H-Index: 13
view all 5 authors...
Cost overruns are prevalent in hydrocarbon (oil and gas) megaprojects. A recent report indicates that 64% of ongoing megaprojects globally are facing cost overruns. Despite their increasing occurre...
30 CitationsSource
#1Atif Ansar (University of Oxford)H-Index: 6
#2Bent Flyvbjerg (University of Oxford)H-Index: 46
Last. Daniel Lunn (University of Oxford)H-Index: 9
view all 4 authors...
A brisk building boom of hydropower mega-dams is underway from China to Brazil. Whether benefits of new dams will outweigh costs remains unresolved despite contentious debates. We investigate this question with the “outside view” or “reference class forecasting” based on literature on decision-making under uncertainty in psychology. We find overwhelming evidence that budgets are systematically biased below actual costs of large hydropower dams—excluding inflation, substantial debt servicing, env...
264 CitationsSource
#1Agnar Johansen (SINTEF)H-Index: 7
#2Bettina SandvinH-Index: 1
Last. Andreas Økland (SINTEF)H-Index: 4
view all 4 authors...
As pointed out by Venkataraman and Pinto (2010), the importance of estimating project costs arises as the estimates become the benchmarks of which future costs are compared and evaluated. Although estimates become more accurate as decisions are made and uncertainties resolved, they are also chief means for assessing project feasibility, as a comparison of cost estimates with estimates of revenues and other benefits that are crucial in determining whether the project is worthwhile to carry out or...
6 CitationsSource
#1Bent FlyvbjergH-Index: 46
#2Niels BruzeliusH-Index: 3
Last. Werner RothengatterH-Index: 14
view all 3 authors...
Back cover text: Megaprojects and Risk provides the first detailed examination of the phenomenon of megaprojects. It is a fascinating account of how the promoters of multibillion-dollar megaprojects systematically and self-servingly misinform parliaments, the public and the media in order to get projects approved and built. It shows, in unusual depth, how the formula for approval is an unhealthy cocktail of underestimated costs, overestimated revenues, undervalued environmental impacts and overv...
7 Citations
#1Robert J. ChapmanH-Index: 1
24 CitationsSource
#1Ole Jonny Klakegg (NTNU: Norwegian University of Science and Technology)H-Index: 11
#2Olav Torp (NTNU: Norwegian University of Science and Technology)H-Index: 5
Last. Kjell Austeng (NTNU: Norwegian University of Science and Technology)H-Index: 3
view all 3 authors...
Purpose – The purpose of this paper is to describe the transfer of experiences to improve the basis for overcoming the dilemma of trying to achieve analyses and systems that are both good and simple. The quality of decisions relating to projects depends on how well the assumed basis for the project actually fit the reality of the situation in which the consequences occur. Good value and cost estimations support good decisions about projects insofar as the assumptions on which they are based mirr...
6 CitationsSource
Construction projects, private and public alike, have a long history of cost escalation. Transportation projects, which typically have long lead times between planning and construction, are historically underestimated, as shown through a review of the cost growth experienced with the Holland Tunnel. Approximately 50% of the active large transportation projects in the United States have overrun their initial budgets. A large number of studies and research projects have identified individual facto...
96 CitationsSource
#2Rajkumar RoyH-Index: 35
Last. Philip WardleH-Index: 4
view all 4 authors...
Contracting for availability is expected to become more prevalent for product -service systems (PSS) in the aerospace and defence industries. These contracts tend to transfer responsibilities for the operational phase from the customer to the supplier. In parallel, with operational life spans spanning several decades, the ability to deal with uncertainty in cost estimation for support activities is becoming critical. This paper outlines challenges within this process derived from literature as w...
49 Citations
Cited By7
Newest
#1Diletta Colette Invernizzi (University of Leeds)H-Index: 5
#2Giorgio Locatelli (University of Leeds)H-Index: 19
Last. Naomi J. Brookes (Warw.: University of Warwick)
view all 3 authors...
Historically, project management research on infrastructure has mostly focused on its planning, design and construction. However, globally, more and more infrastructure, such as nuclear power plant...
Source
#1Terry Williams (University of Hull)H-Index: 34
#2Hang Vo (University of Hull)H-Index: 1
Last. Andrew Edkins (UCL: University College London)H-Index: 9
view all 4 authors...
AbstractThis paper summarizes the results of a comprehensive systematic literature survey on the front-end of a project, commissioned by the Project Management Institute. The dedicated literature o...
2 CitationsSource
#1Ayodeji Olatunji Aiyetan (Durban University of Technology)
#2Naidoo Ashok (Durban University of Technology)
Implementing a suitable plan, design and management strategy is critical to the success of a project. Project delivery challenges encountered within the built-environment is a global phenomenon. Factors causing project delivery challenges in construction projects differ between countries, due to various fundamental reasons. The aim of the study is to assess lack of performance and its effects on project delivery for construction infrastructure projects with reference to Umgeni Water. The study w...
Source
#1Diletta Colette Invernizzi (University of Leeds)H-Index: 5
#2Giorgio Locatelli (University of Leeds)H-Index: 19
Last. Naomi J. Brookes (University of Leeds)H-Index: 16
view all 4 authors...
Abstract The vast majority of project management literature relating to infrastructure focuses on the project lifecycle up to commissioning and handover. Conversely, little attention has been paid to the end-of-life of infrastructure, i.e. when decommissioning begins. Infrastructure decommissioning projects are long and complex projects, involving an extensive network of stakeholders. Moreover, their budgets can reach hundreds of billions of Euros and, for many of these projects, keep increasing...
Source
#1Linlin Zhao (Beijing University of Technology)H-Index: 2
#2Jasper MbachuH-Index: 9
Last. Huirong Zhang (Beijing University of Technology)
view all 4 authors...
An accurate cost estimate not only plays a key role in project feasibility studies but also in achieving a final successful outcome. Conventionally, estimating cost typically relies on the experience of professionals and cost data from previous projects. However, this process is complex and time-consuming, and it is challenging to ensure the accuracy of the estimates. In this study, the bivariate and multivariate transfer function models were adopted to estimate and forecast the building costs o...
Source
#1Olav TorpH-Index: 5
#2Ingemund JordangerH-Index: 1
view all 4 authors...
Purpose The purpose of the paper is 1) to address the importance of contingency at the right level when defining project control baseline, including cost reserves / “room to manoeuvre” and 2) present proactive uncertainty management as a regime to ensure cost effective management of project reserves and contribute to project success. Design/Methodology/Approach The paper is a combination of literature study and quantitative research on how contingency develops during the lifetime of a case proje...
Source
#1Diletta Colette Invernizzi (University of Leeds)H-Index: 5
#2Giorgio Locatelli (University of Leeds)H-Index: 19
Last. Naomi J. Brookes (University of Leeds)H-Index: 16
view all 3 authors...
Abstract Nuclear Decommissioning Projects and Programmes (NDPs) are characterized by high complexity and variety, and a schedule that can take decades. Moreover, NDPs estimates at completion can reach billions of Euro and (for many of these projects) keep increasing, while there is a limited understanding of why this happens. To address this knowledge gap, this paper describes how to statistically test the association between the NDP characteristics and the NDP cost performance. The implementati...
1 CitationsSource
#1Diletta Colette Invernizzi (University of Leeds)H-Index: 5
#2Giorgio Locatelli (University of Leeds)H-Index: 19
Last. Naomi J. Brookes (University of Leeds)H-Index: 16
view all 3 authors...
Abstract Nuclear Decommissioning Projects and Programmes (NDPs) are jeopardized by several risks, long schedule and cost estimates that lay in the range of hundreds of billions of pounds. Moreover, in some countries, these estimates keep increasing and key stakeholders have a limited understanding of the determinants that engender this phenomena. Benchmarking refers to the process of comparing projects in order to identify best practices and generate ideas for improvement. However, even if it is...
5 CitationsSource
The idea behind this Special Issue is based on the observation that project risk management is presented as a key knowledge area in project management and has become an important skill for updated project managers [1,2].[...]
2 CitationsSource