A project buffer and resource management model in energy sector; a case study in construction of a wind farm project

Volume: 14, Issue: 6, Pages: 1123 - 1142
Published: Apr 21, 2020
Abstract
Purpose This study aims to introduce an efficient project buffer and resource management (PBRM) model for project resource leveling and project buffer sizing and controlling of project buffer consumption of a wind power plant project to achieve a more realistic project duration. Design/methodology/approach The methodology of this research consists of three main phases. In the first phase of the research methodology, resource leveling is done in...
Paper Details
Title
A project buffer and resource management model in energy sector; a case study in construction of a wind farm project
Published Date
Apr 21, 2020
Volume
14
Issue
6
Pages
1123 - 1142