A two-stage approach for the critical chain project rescheduling

Volume: 285, Issue: 1-2, Pages: 67 - 95
Published: Aug 12, 2019
Abstract
The fundamental principle of critical chain project management is to use the critical chain instead of a traditional critical path, to insert a project buffer at the end of the project and to insert feeding buffers wherever non-critical chains join the critical chain to protect a timely project completion. Due to the complexity of project, inserting feeding buffers may cause a conflict, such as precedence conflict or resource conflict, which can...