Comparison of cost and schedule performance of large public projects under P3 and traditional delivery models: a Canadian study

Volume: 38, Issue: 8, Pages: 739 - 755
Published: Aug 2, 2019
Abstract
Cost overrun and schedule delay are pervasive in large public infrastructure projects in Canada and there is an ongoing debate over the root causes of these delivery risks and how best to mitigate them. Since public-private partnerships (P3s) have been long touted as an effective mitigating measure, this study aimed to provide comparative empirical evidence to explore this claim. By collecting cost and schedule data at three key milestones...
Paper Details
Title
Comparison of cost and schedule performance of large public projects under P3 and traditional delivery models: a Canadian study
Published Date
Aug 2, 2019
Volume
38
Issue
8
Pages
739 - 755
Citation AnalysisPro
  • Scinapse’s Top 10 Citation Journals & Affiliations graph reveals the quality and authenticity of citations received by a paper.
  • Discover whether citations have been inflated due to self-citations, or if citations include institutional bias.