ESTIMATING NORMAL DURATION OF RENOVATION FOR MULTISTORY APARTMENT BUILDING CONSIDERING EXTENSION-TYPE RENOVATION PROJECTS

Volume: 25, Issue: 2, Pages: 156 - 167
Published: Feb 25, 2019
Abstract
Normal (typical) project duration is estimated at the initial stage of a renovation project and is an important reference for project control. However, its estimation has not been researched extensively owing to the complexity and uncertainties of renovation. Thus, a model was developed for predicting the duration of sustainable apartment renovation. Experts were asked to estimate a baseline schedule for extension-type renovation projects,...
Paper Details
Title
ESTIMATING NORMAL DURATION OF RENOVATION FOR MULTISTORY APARTMENT BUILDING CONSIDERING EXTENSION-TYPE RENOVATION PROJECTS
Published Date
Feb 25, 2019
Volume
25
Issue
2
Pages
156 - 167
Citation AnalysisPro
  • Scinapse’s Top 10 Citation Journals & Affiliations graph reveals the quality and authenticity of citations received by a paper.
  • Discover whether citations have been inflated due to self-citations, or if citations include institutional bias.