Improved Baseline Method to Calculate Lost Construction Productivity
Abstract
The measured mile/baseline method has been widely accepted to quantify labor productivity loss, which is demonstrated by comparing the impacted and unimpacted/lightly impacted portions of the work. Although the distinctions between these portions of a project can at times be identified through a cause and effect analysis, on many projects this distinction is not readily observable. For those projects, researchers and professionals have developed...
Paper Details
Title
Improved Baseline Method to Calculate Lost Construction Productivity
Published Date
Feb 1, 2014
Volume
140
Issue
2
Citation AnalysisPro
You’ll need to upgrade your plan to Pro
Looking to understand the true influence of a researcher’s work across journals & affiliations?
- Scinapse’s Top 10 Citation Journals & Affiliations graph reveals the quality and authenticity of citations received by a paper.
- Discover whether citations have been inflated due to self-citations, or if citations include institutional bias.
Notes
History